The first phase of a revamp to improve Brightlingsea’s much-loved promenade and make it more accessible is nearing completion.
Residents and visitors are warned there will be limited or no access around Splash Point during the week commencing 30 November while Tendring District Council (TDC) joins the new promenade surface to the existing stretch.
The work forms part of improvements to the promenade around the paddling pool, addressing long-standing wear and tear and creating a smoother surface with better drainage.
Weather permitting, the first section is expected to be fully accessible before Christmas, with the remaining work taking place around suitable tides.
Councillor Adrian Smith, TDC’s Cabinet Member for Environment, which includes responsibility for Coast Protection and Engineering, said: “These works are addressing long-standing wear and tear, creating a smoother, more accessible surface and improving drainage around the paddling pool.
“Subject to suitable tides and weather, we’re aiming to have this first section fully accessible before Christmas, with the next phase getting under way in February.
“We apologise for the disruption to access during the works, but we’re confident residents will appreciate the revamped promenade once the work is finished.”
Councillor Mick Barry, TDC’s Cabinet Member for Leisure and Public Realm, added: “Local residents and district councillors have long championed improvements to this much-loved stretch of seafront, and I’m delighted we’ve secured the investment to make them happen.
“It is great to see the first phase nearing completion, creating a more welcoming promenade for everyone who enjoys spending time in Brightlingsea.”
With no suitable working tides in January, phase two is scheduled to begin in the first week of February 2027.
Work will then take place on alternate weeks around the tides, with a break for the Easter holidays. Phase two is expected to require approximately five to six working weeks, rather than consecutive calendar weeks.