Week 22
This week sees the near completion of the new Lifestyles gym.
99% of the carpet is now laid, and it's really starting to look
like a gym!

In the dance studio mirrors have been installed. Ballet
anyone?!

Works on the new cafe area have continued, with the initial
framework for the wall and windows going in and also works to the
new gas main being carried out:

Next we have new drainage going in the dryside area and rails
for the new pool ceiling now up:

The electricians have been in the office this week trying to
sort what can only be described as spaghetti junction above the
ceiling tiles, removing old wiring and installed new. Here's a
before (oh dear) and after (nice and neat) view:

Finally we have the spa extension, showing some of the details
of the spa pool itself and surrounding areas.
Here you can see the new step at the shallow end of the spa pool
and the jets going in:

and here is a new natural light feature and floor tiles laid in
the new steam room:

Week 21
This week progress has been steady, and things are really taking
shape up in the new gym.
Here you can see the carpet going down, the new free weights
area and the internal windows installed:

Works have also continued up in the new spa/gym changing rooms,
with the under floor heating going in everywhere:

Works are also going really well downstairs in the dryside
area.
Here you can see drainage being dug out and new walls going
up:

Next we have the pool hall, with works on the new ceiling coming
along nicely - although it does look a bit of a mess! The
electricians have been fitting new cabling:

More walls and rooms have gone up in the spa area and with
further works to the spa pool itself, its really getting there.
Here you can see saunas and steam rooms etc going up and more
pipe work and walls in the spa pool:

And finally, works on sprucing up the front of the building have
begun: