Week 1
Here we go! Hutton's work site is established:

and the work begins. Its mainly boarding up and demolition at
the moment! This was the kiosk and outside changing area:

and now they're gone:

Week 2
Work begins in and around different areas of the building:
Boarding is erected in the dryside locker room; this is to
continue works on the new poolside staircase and redeveloping the
back corridor and spa/changing room extension:

Due to this work, a temporary access to the outside areas is
created via the ancillary hall side gate:

Work begins on a new fire exit at the deep end of the pool
hall:

Work also began in the ancillary hall. Basket ball rings were
dismantled whilst heaters and electrics were stripped:

The flooring is cut into ready to start on foundations:

and this is now on my Christmas List!!

Demolition work continues in the bar/cafe area:

and now were beginning to get there:

The old upstairs staff room suddenly has a new window!

The bar balcony is boarded up (and gains some unusual patio
furniture!)

Finally, work begins on the foundations of the new Spa and
changing extension:

Week 3
Work continues on the pool staircase - after
several full nights work, the old pool balcony staircase is just
about gone and work can commence on the new staircase leading up
from the current dry side locker room:

A temporary staircase is erected on poolside for emergency use
when the new staircase opens:

Spa Extension - The area has been marked out
and several sections have been dug up and filled with concrete:

Continued demolition in the bar area - Really
beginning to open up the space upstairs - I didn't realise how big
it was until now!:


Real progress being made in the Ancillary Hall
- areas are dug out for pillar foundations:


Once dug, the holes are filled with concrete: