Week 16
Well, deciding where to begin was the hardest thing this week as
there seems to be so much progress made in nearly all areas.
The first thing to catch your eye is the new cafe extension:
 
The outer wall foundations and bases are really taking
shape.
 
More brickwork continues on the inside.
 
Upstairs in the new gym the floor is in the process of being
filled with concrete and screed.

The new windows are taking shape in the reception area.
 

The ducting for the new Air Handling Unit is progressing
well

Moving on to the new spa extension:
 
The spa pool has been built up:
 
The new double staircase is taking shape:

Work has also begun on the first floor changing facilities:


All mod cons with new toilet and shower facilities:
 
The Energy drink is proof of how hard the builder are
working:

Last, but not least, the ground floor ancillary hall, which is
due for completion this week, ready to house the gym.

Plans for next week include completion of the ancillary hall and
possible delivery of the spa tank.
Week 15
Further progress has been made this week in both
the ancillary hall and new gym area upstairs.
Starting with upstairs, a lot of brickwork has
been completed on the old bar balcony. You can see the new
extension, where the windows will be, the new window/door frames in
the dance studio and the new frames for the pool balcony
viewing:
 
 
Works have also continued out on the spa extension with the
exterior wall almost complete and the final foundations for the spa
tank. There are also 2 new staircases being built:
 
 
Works have continued on the new cafe extension:
 
Works planned for the coming week include:
Further roofing works on spa extension
- Possible completion of the ground floor of the ancillary
hall
- More works upstairs
Week 14
Plenty happening again this week, with several areas progressing
nicely. First off, we have the new cafe extension on the front of
the building:
Crane hoisting metal work in place; taking shape above the
hoardings and an internal view:
  
Upstairs has really taken shape, with the sprung flooring being
laid in the dance studio:
Men hard at work and almost complete, bar the skirting:
 
Further works to flooring in the new gym area have been
completed, with casings going in ready to hold all electrical
cables for the machines. Plus the installation of the new air
conditioning units:
Gym flooring, with areas dug out and the new air conditioning
units going in:
 
Works on bar balcony continue and the new extension
roofing:
 
Further brickwork and construction has taken place on the new
spa extension:
Showing where the windows from the new spa will be and the wall
adjacent to the artificial pitch:
 
Showing what will be the rear exit to outside areas; foundations
for new staircase and the spa area:
  
Planned works for the coming week include:
- Continued works on cafe extension
- Possible delivery and installation of new spa tank
- Further progress upstairs in the gym and downstairs in
ancillary hall
View Weeks 11 to 13
here |