Tendring DC Logo

Past Blogs Weeks 32-34


Weeks 34

With the proposed final week coming up, things are coming up to the completion stage.

We start in the dryside area with new corridors and a meeting room that is ready to use:

Image of the dryside corridor Image of the meeting room

The new admin. suite just needs the final touches and the poolside balcony is freshly decorated:

Image of the admin suite Image of the pool seating

Next we have the cafe and front entrance:

Image of the front entrance Image of the cafe

And finally we have the spa and changing room extension:

Image of the spa Image of the spa changing area

Image of the spa extension Image of the back door

And that concludes this weeks update. With completion due this coming week, watch out for the final blog and a look back at the overall development.

Weeks 33

This week see's the near completion of several areas and with only a week to two left, the overall development is drawing to a close.

We begin with the dryside area:

New dryside entranceOpen plan locker areaNew changing areaVanity unitsOffice with a view

Next we have the new admin suite and corridor:

New corridor New admin suite, nearly complete

And next is the new cafe:

Just the decorating left to finishCafe serving area

The spa area is now 99% complete:

Very invitingOnly a few minor touches left to finish

And finally we have the newly installed CCTV cameras:

All fully operationalAble to monitor everywhere in the centre

That concludes this week's update and with only minor work loads to complete, keep an eye out for next week's blog to see how things turn out!

Weeks 32

Progress this week has been steady, with more areas on their way to completion. We start at the front entrance:

Block paved entranceOffice roof is now up.

Next we come to the dyside corridor, lock areas, gents changing and the admin suite:

New dryside corridorLocker area

New gents changing areaAdmin suite ceiling is now in

Then comes the new ancillary hall floor:

Ancillary hall all done

And finally the cafe area:

Cafe ceiling now completeMore of the cafe

Now long left now, so be sure to check out next weeks' update.

View Weeks 27 to 31 here

View Weeks 23 to 26 here

View Weeks 21 to 22 here

View Weeks 17 to 20 here

View Weeks 14 to 16 here

View Weeks 11 to 13 here

View Weeks 7 to 10 here

View Weeks 4 to 6 here

View Weeks 1 to 3 here



Page Last Updated
01 January 2009